[ Online ] 06/08/2022
 
Rampal Power Plant: 80% progress, production starts in October
The Rampal Thermal Power Plant in Khulna will go for generating electricity in October this year as 80% of its infrastructural development has already been completed, project officials said on Friday.

Besides, the first shipment of coal for the power plant from Indonesia has already arrived at Mongla Port, paving the way for electricity production this year, said the power plant's Deputy General Manager Anwarul Azim.

He also said "The first unit of this plant under the Bangladesh-India Friendship Power Company Limited (Bifpcl) will add electricity to the national grid from October if all are okay. Besides, the 2nd unit will add electricity to the national grid in February 2023."

DGM Anwarul Azim said, "The Bangladesh flag-bearer "MV Akij Heritage" carrying 55,000 tonnes of coal arrived at Chattogram port from Indonesia. From there, three lighter vessels ferried 18,650 tonnes of coal to the terminal of the power plant and they started unloading it on Thursday afternoon."

"From now on, coal will be supplied to the plant on a regular basis. It will be operated experimentally from this month," he said.

At first, Bangladesh signed a contract to import 3 lakh tonnes of coal from Indonesia for the power plant.